Thursday, August 20, 2015

Day 45: More HVAC and concrete

Today we met with our Guardian rep and went through the house and marked the locations of all the low-voltage items.  First thing we noticed was the concrete for the porch was poured and the shingles were almost finished, they literally have like 10 left to put down.  HVAC guys made a lot of progress on the 2nd floor, they had just about all the ducts in place and the furnace was installed.  Some progress was made on the first floor as well.  Looks like our project manager also went through and marked things with orange spray paint that needed fixed.