Day 95: HVAC returns and basement insulation.

On Friday the HVAC crew came back and finished hooking up furnaces and ac units. Although the ac units could use some leveling.  The basement walls were insulated and all the doors were hung back up after being painted. 








3 comments:

  1. It looks like they put your electrical panel in the doorway under the steps. They did the sale thing with mine, the put the panel 20% under the steps and 80% in the storage room. We were planning to have our storage room door there which could be an issue now since they put the panel where we were going to put our door.

    ReplyDelete
    Replies
    1. I actually wanted it there under the steps so it worked out. Later down the line when we finish the basement we are making the back room a bedroom. With the panel area drywalled it does look like it is in the door area, but it isn't.

      Delete
  2. It looks like they put your electrical panel in the doorway under the steps. They did the sale thing with mine, the put the panel 20% under the steps and 80% in the storage room. We were planning to have our storage room door there which could be an issue now since they put the panel where we were going to put our door.