Monday, October 26, 2015

Day 112: Quality Inspection

Today is the quality inspection.  Over the past few days they've been going through their punch list and fixing any issues.  They came and replaced the scratched hardwood and hopefully it stays scratch free this week.  We are still waiting to hear back from rite rug as they are supposed to have some tile selections for us to pick from to trim around the window in our shower since their tiling crew screwed that up.  Our pre-settlement walk-thru is this Wednesday with closing to follow Friday morning.





4 comments:

  1. Our pre-settlement walk through is Friday afternoon. We still do not have a settlement date.

    ReplyDelete
  2. Our pre-settlement walk through is Friday afternoon. We still do not have a settlement date.

    ReplyDelete