The framing crew was there today and seem to have finished everything that would need done to begin drywalling.  The concrete was cut out at the garage door sill and they came back to fix the issue with that, although it still seems like it's crooked.  Insulation will start tomorrow, but they did do some spray foam insulation on the garage ceiling and at the ceiling level in the basement on the exterior walls.  Tomorrow is pre-drywall meeting so we will meet with out project manager and go over anything we think needs changed or fixed before they button it all up.